Localized pothole repair
on bituminous pavement
Standard Operating Procedure · LL-TEQ™ (APH) system — Asphalt Pothole Mix
Standard Operating Procedure (SOP)Pothole repair on asphalt
LL-TEQ™ (APH) system « Asphalt Pothole Mix » — LL30 (binder) + crushed aggregate 0–12.5 mm + LL25 (seal)
Purpose & scope
Standardized method for the localized (spot repair) repair of potholes on bituminous pavement using the LL-TEQ™ (APH) system — « Asphalt Pothole Mix », formulated specifically for this application: cleanout down to stable soil below, rebuilding the cavity with LL30 + crushed aggregate 0–12.5 mm (0–½ in) compacted to refusal, then surface sealing with LL25. Intended for municipal road-maintenance crews using standard road-maintenance equipment.
Key requirement: cleanout onto stable soil below to a minimum depth of 150 mm (6 in), rebuild with LL30 + aggregate 0–12.5 mm (0–½ in) compacted to refusal, then seal with LL25.
Required qualification: the work must be carried out by an accredited LL-TEQ™ installer. Accreditation is earned upon completing the LL-TEQ™ training, which teaches mix preparation, dosage, compaction to refusal, and the cure and reopening criteria. The accredited installer executes the procedure in accordance with this SOP and judges reopening.
Materials
Constituents of the LL-TEQ™ (APH) system
| Constituent | Specification | Role |
|---|---|---|
| Aggregate | Crushed stone 0–12.5 mm (0–½ in), dry, free of organic matter. | Structural fill material for the cavity |
| LL30 | Structural binder — APH formulation for pothole repair. | Cohesion and load-bearing of the compacted fill |
| LL25 | Surface seal — APH formulation for pothole repair. | Surface water-tightness of the repaired joint |
| Water | Misting of the mix per conditions. | Maintaining mix moisture |
Reference dosage
34.5 L of LL30 per m³ of stone, i.e. ≈ 5.25 L of LL30 per m² of aggregate placed over 150 mm (6 in) of compacted thickness.
Mix design — batch of 6 holes
Calculated quantities and batch preparation
Calculation assumption
Typical hole: 600 × 600 × 150 mm (24 × 24 × 6 in) ≈ 57 L of stone per hole.
Quantities per batch of 6 holes
- Stone 0–12.5 mm (0–½ in) dry: 6 × 57 L ≈ 342 L
- LL30: 342 L × 34.5 L/m³ ≈ 12 L
Preparation procedure
- Load the mixer: stone + LL30 at the 34.5 L/m³ dosage.
- Mix for a few minutes until uniform integration — even colour, texture and moisture, aggregate fully coated by the binder.
- Empty into the handling container (bin). Repeat batches until the batch volume is reached.
- Tarp the bin: in the shade, sheltered from direct sun and rain.
- Use the batch within 3 h of mixing.
- Mist water onto the mix every hour to maintain moisture, especially in hot weather.
- Beyond 3 h, keep using the mix while maintaining misting until the batch is used up.
Critical parameter: moisture. Hourly misting keeps the mix moist until placement — a direct condition for reaching target compaction.
Site equipment
Suggested equipment — any equivalent is acceptable
Carrier vehicle
Pickup or trailer for the mixer, bin, materials and tools.
Asphalt saw — optional
Optional, for clean finished edges. Diamond blade — suggested: Husqvarna K770 or equivalent.
Hand tools
Pick, shovel, wheelbarrow, broom — extraction and cleaning of the cavity.
Site concrete mixer
Usable capacity ≥ 100 L per batch (≈ 180 L drum).
Mix container
Low, wide bin ≈ 400 L (tub, open crate or bulk bag) with easy shovel access + waterproof tarp.
Hand sprayer (water)
Misting — suggested: 5–8 L pressure sprayer or equivalent.
LL25 applicator
Calibrated hand sprayer — suggested: Rosco Maxigill or ETNYRE for high volume; dedicated pressure sprayer for spot repairs.
Straightedge / level
Check of the final grade, flush with the adjacent surface.
Compaction — two equipment options
Field procedure
Execution sequence — minimum cleanout depth: 150 mm
Delimitation
Mark out the zone set back from the visible defect, onto sound material. Optional sawing (asphalt saw) for clean edges: straight cuts, perpendicular to the surface, through the full thickness of the asphalt.
Cleanout & cleaning of the cavity
Remove the degraded material to a minimum depth of 150 mm (≈ 6 in). Blow or sweep out the cavity (dust, debris, standing water). Make sure the soil below is stable before continuing.
Placing the mix
- 50–80 kg plate: in 2 lifts of ≈ 75 mm (3 in), compaction to refusal after each lift.
- 90–120 kg plate: in a single 150 mm (6 in) lift, compaction to refusal.
Slight overfill above the adjacent surface to compensate for settlement under compaction. Spread evenly, with attention to corners and edges.
Compaction to refusal
Compact to refusal — no deformation, no imprint under the machine. Target: 95%+. Cross-pattern passes, with particular attention to edges and the joint with the existing surface. Check the final grade, flush with the adjacent surface — with no ridge, bump or depression at the joint.
Surface sealing — LL25
Once the LL30 has begun its initial set (stable surface, no pull-off to the touch), apply LL25 by uniform spraying until the surface is fully saturated. Overlap the seal onto the adjacent intact surface to ensure joint continuity. Additional passes until visible saturation.
Cure & reopening to traffic
Minimum 12 h cure depending on conditions, until the surface is rigid and the cure complete: stable to the touch, no material transfer, LL25 dry at the surface. Curing proceeds faster in hot, dry, well-ventilated weather; high humidity or low temperature lengthen cure time. Protect from rain during the initial cure. The accredited installer's judgement, based on observed stability, governs reopening.
Quality control & acceptance criteria
Check points during and at the end of execution
| Ref. | Check point | Acceptance criterion |
|---|---|---|
| QC-1 | Cavity edges | On sound material, clean |
| QC-2 | Soil below | Stable, no soft spots, no standing water |
| QC-3 | Depth | ≥ 150 mm (6 in) |
| QC-4 | LL30 integration | Uniform mix, aggregate fully coated |
| QC-5 | Mix moisture | Misting maintained, mix moist at compaction |
| QC-6 | Compaction | 95%+; refusal reached |
| QC-7 | Final grade | Flush, no ridge or depression |
| QC-8 | LL25 seal | Full saturation, overlapping onto adjacent surface |
Execution conditions
Environmental and placement preconditions
- Substrate not frozen.
- Ambient and substrate temperature > 5 °C.
- LL25 requires at least 3 h without rain after application; do not apply the seal if rain is possible within 3 h. Rain dissolves LL25 and prevents it from integrating (redo required).
- Avoid rain during application and cure; substrate not saturated.
- Aggregate kept dry before mixing.
- Mix tarped, in the shade, moistened as needed.
- Fill material free of organic matter.